35 workers are employed to complete a construction in 16 days. the boss needs to complete the project in 14 days. all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time...? Mcqs

Latest MCQs

35 workers are employed to complete a construction in 16 days. the boss needs to complete the project in 14 days. all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time...?

(A) 3
(B) 4

(C) 5
(D) 9

Latest MCQs

1, 9, 25, 49,_____________121...?

(A) 100
(B) 81

(C) 91
(D) 94

Latest MCQs

The diameter of a wheel of a car is 48 cm. If the car travels at an average speed of 3,5 km/h. The number of revolutions made by the wheel per minute is:...?

(A) 09
(B) 19

(C) 29
(D) 39

Latest MCQs

21 binders can bind 1400 books in 15 days How many binders will required to bind 800 books in 20 days...?

(A) 7
(B) 9

(C) 12
(D) 14

Latest MCQs

How many two digit numbers are divisible by 11...?

(A) 7
(B) 8

(C) 9
(D) 11

Latest MCQs

A sum of money becomes doubles in 3 years at compound interest, compounded annually at the same rate. In how many years it will become 4 times of itself...?

(A) 5 years
(B) 6 years

(C) 7.5 years
(D) 12 years

Latest MCQs

Aslia has three types balls red, green and blue. If their ratio is 2:3:5 what percent of balls are green...?

(A) 20%
(B) 30%

(C) 45%
(D) 50%

Latest MCQs

Which One Number will complete the form number series..? 4, 11, 7, 14, 10

(A) 21
(B) 13

(C) 12
(D) 18

Latest MCQs

By converting 75% into fraction, answer will be:...?

(A) 3/4
(B) 2/3

(C) 1/3
(D) 1/4

Latest MCQs

A man annual production sells in 3481600 The use of 10% will be...?

(A) 35000
(B) 34816

(C) 34670
(D) None of these

Best of Luck

From ShineGk.com

Share our website's link